About This Project

Whilst carrying out some routing sea wall repairs we highlighted an area of the sea wall that had been undermined and that had also undermined the footpath and was affecting the road. We worked swiftly to liaise with the local authority to close the road and carry out a swift repair to ensure the road was open again as soon as possible, whilst we carried out these works a further survey of the area was carried out and identified another hole further along the seafront which also swiftly repaired. These two holes were approximately 200t in size. We spotted the problem and carried out the necessary repairs within 1 week.

Category
Civil, Maintenance